No. |
Contracts Undertaken |
Client |
Contract Duration |
Contract Location / Country |
|
Start Date |
End Date |
||||
1 |
Provision of Supply and Commissioning Service of Power Supply Skid for Field Surface Facilities (FSF) Project Supply, Delivery and Commissioning for: ● Hundreds of Power Supply Skids(11/0.4kV substation) |
Petro-Energy |
Jul., 2012 |
Apr., 2019 |
Sudan |
2 |
Provision of Supply and Commissioning Service of Power Supply Skids for Filed Surface Facilities Phase-1 (FSF1 ) Project and Power Distribution Network Project Supply, Delivery and Commissioning for: ● 33KV Power Supply Skids |
Staroil |
Jan., 2012 |
May 2016 |
Sudan |
3 |
Provision of Supply and Commissioning Service of Power Supply Skid for Field Surface Facilities (FSF) Project Supply, Delivery and Commissioning for: ● More than one hundred sets of Power Supply Skids(11/0.4kV substation) |
Petro-Energy CPECC |
Sep., 2009 |
Jan., 2018 |
Sudan |
4 |
Provision of Supply and Commissioning Service of Power Supply Skid for Field Surface Facilities (FSF) Project Supply, Delivery and Commissioning for: ●More than sixty sets of Power Supply Skids (11/0.4kV substation) |
Petro-Energy RAM |
Nov., 2009 |
Apr., 2019 |
Sudan |
5 |
Provision of Supply and Commissioning Service of Power Supply Skid for FSF and transit Line of Phase-3 Upstream Facilities Supply, Delivery and Commissioning for: ● More than forty sets of Power Supply Skids (11/0.4kV substation) |
Petro-Energy DUPEC |
Jun., 2009 |
Jun., 2010 |
Sudan |
6 |
Provision of Supply and Commissioning Service of Power Supply Skid for Field Surface Facilities (FSF) Project Supply, Delivery and Commissioning for: ● More than thirty sets of Power Supply Skids(11/0.4kV substation) |
Petro-Energy Petroneeds |
Sep., 2013 |
Mar., 2019 |
Sudan |
7 |
Provision of Supply and Commissioning Service of Power Supply Skid for Field Surface Facilities (FSF) Project Supply, Delivery and Commissioning for: ● Power Supply Skids(11/0.4kV substation) |
Petro-Energy Asawer |
Apr., 2013 |
Mar., 2019 |
Sudan |
8 |
Provision of Procurement, Construction, and Commissioning Service of for Huambo and Ka Ala MV/LV Distribution Network Reconstruction Project Procurement, Construction, and Commissioning for: ● Almost 50 units of 11KV /0.4KV Power Supply Skid ● 11KV Overhead Transmission Line (38KM) ● 11KV, 0.4KV Underground Cable(5KM) |
National Power Company of Angola(ENE) SPTD |
Oct., 2009 |
Oct., 2011 |
Angola |